AI infrastructure power · Large-load interconnection · CARTA-LOADQ-ERCOT-DC_SHARE-2026-02-25-001
Data-center share of queued load
74.4%
As of 25 Feb 2026 · Electric Reliability Council of Texas (ERCOT) · Outdated as of 27 Mar 2026 Permalink
Record
- Filter, as published
ERCOT slide "Large Load Project Distribution by Type", pie chart label for category "Data Center" (share of tracked large load, with MW).
- Category
- AI infrastructure power · Large-load interconnection
- Object
- ercot_large_load_queue
- Measure
- Data-center share of queued load (load_dc_share)
- Family
- large_load_queue · load
- Geography
- ERCOT · US
- Organization
- ERCOT
- Claim type
- Official extract
- Method
- OCR (RapidOCR, 2 agreeing passes) of the chart label on slide 12. Raw sha256 a4cc69d18ea1. Verified against the source file on 2026-09-14 by TechCarta's automated checks: table values were read twice by OCR and matched, columns sum to their printed totals, and each value was compared with the slide image. Approved for publication by C.J. Fernandes.
- Source
- Electric Reliability Council of Texas (ERCOT), Large Load Interconnection Status Update
Grid operator (primary) · retrieved 14 Sep 2026
https://www.ercot.com/files/docs/2026/03/05/February-TAC-Report.pdf
Archived copy (identical file) - Evidence
- Outdated as of 27 Mar 2026 Past its re-check date. Describes the evidence recorded for this claim, not whether it is true. How this is decided
- Re-check after
- 27 Mar 2026 (30 days after the as-of date)
- Notes
- The label's share and MW imply a denominator of about 235,382 MW; the queue total on the same deck's table is 237,712 MW.
- License
- cite_source
Cite this Carta
Plain text
Electric Reliability Council of Texas (ERCOT). (2026). Large Load Interconnection Status Update [Data-center share of queued load: 74.4%, as of 2026-02-25]. Retrieved 2026-09-14, from https://www.ercot.com/files/docs/2026/03/05/February-TAC-Report.pdf. Recorded in TechCarta, CARTA-LOADQ-ERCOT-DC_SHARE-2026-02-25-001. https://techcarta.com/carta/CARTA-LOADQ-ERCOT-DC_SHARE-2026-02-25-001/
BibTeX
@misc{carta_loadq_ercot_dc_share_2026_02_25_001,
author = {{Electric Reliability Council of Texas (ERCOT)}},
title = {Large Load Interconnection Status Update: Data-center share of queued load, 74.4\% (as of 2026-02-25)},
year = {2026},
howpublished = {\url{https://www.ercot.com/files/docs/2026/03/05/February-TAC-Report.pdf}},
note = {TechCarta Carta CARTA-LOADQ-ERCOT-DC_SHARE-2026-02-25-001; source retrieved 2026-09-14},
url = {https://techcarta.com/carta/CARTA-LOADQ-ERCOT-DC_SHARE-2026-02-25-001/}
} This Carta is a TechCarta record, free to read and cite. Use of it requires citation. The underlying source belongs to its publisher.