AI infrastructure power · Operating load · CARTA-OPLOAD-ERCOT-PEAK_SIMULTANEOUS-2026-03-13-001
Observed large-load peak consumption
3,801MW
As of 13 Mar 2026 · Electric Reliability Council of Texas (ERCOT) · Outdated as of 12 Apr 2026 Permalink
Record
- Filter, as published
ERCOT slide "Loads Approved to Energize – Observations 2", verbatim: "ERCOT has observed a simultaneous monthly peak consumption of 3801 MW in March 2025 which is a slight decrease since February 2025." Defined by ERCOT as "the maximum value of the sum of all the individual loads per month".
- Category
- AI infrastructure power · Operating load
- Object
- ercot_large_load_queue
- Measure
- Observed large-load peak consumption (funnel_metered_peak_mw)
- Family
- operating_load · load
- Geography
- ERCOT · US
- Organization
- ERCOT
- Claim type
- Official extract
- Method
- Text layer of slide 7, exact sentence match; no OCR. Raw sha256 e152e34d90e3. Verified against the source file on 2026-09-14 by TechCarta's automated checks: table values were read twice by OCR and matched, columns sum to their printed totals, and each value was compared with the slide image. Approved for publication by C.J. Fernandes.
- Source
- Electric Reliability Council of Texas (ERCOT), Large Load Interconnection Status Update
Grid operator (primary) · retrieved 14 Sep 2026
https://www.ercot.com/files/docs/2026/03/12/March-TAC-Report.pdf
Archived copy (identical file) - Evidence
- Outdated as of 12 Apr 2026 Past its re-check date. Describes the evidence recorded for this claim, not whether it is true. How this is decided
- Re-check after
- 12 Apr 2026 (30 days after the as-of date)
- Notes
- ERCOT's sentence names "March 2025" in a deck dated 2026-03-13. Recorded verbatim; the month may be a typo in the source.
- License
- cite_source
Related Cartas
Conflicts with
Cite this Carta
Plain text
Electric Reliability Council of Texas (ERCOT). (2026). Large Load Interconnection Status Update [Observed large-load peak consumption: 3,801 MW, as of 2026-03-13]. Retrieved 2026-09-14, from https://www.ercot.com/files/docs/2026/03/12/March-TAC-Report.pdf. Recorded in TechCarta, CARTA-OPLOAD-ERCOT-PEAK_SIMULTANEOUS-2026-03-13-001. https://techcarta.com/carta/CARTA-OPLOAD-ERCOT-PEAK_SIMULTANEOUS-2026-03-13-001/
BibTeX
@misc{carta_opload_ercot_peak_simultaneous_2026_03_13_001,
author = {{Electric Reliability Council of Texas (ERCOT)}},
title = {Large Load Interconnection Status Update: Observed large-load peak consumption, 3,801 MW (as of 2026-03-13)},
year = {2026},
howpublished = {\url{https://www.ercot.com/files/docs/2026/03/12/March-TAC-Report.pdf}},
note = {TechCarta Carta CARTA-OPLOAD-ERCOT-PEAK_SIMULTANEOUS-2026-03-13-001; source retrieved 2026-09-14},
url = {https://techcarta.com/carta/CARTA-OPLOAD-ERCOT-PEAK_SIMULTANEOUS-2026-03-13-001/}
} This Carta is a TechCarta record, free to read and cite. Use of it requires citation. The underlying source belongs to its publisher.