TechCartaEvidence map

AI infrastructure power · Operating load · CARTA-OPLOAD-ERCOT-PEAK_NONSIMULTANEOUS-2026-02-25-001

Observed large-load peak consumption

3,998MW

As of 25 Feb 2026 · Electric Reliability Council of Texas (ERCOT) · Outdated as of 27 Mar 2026 Permalink

Record

Filter, as published
ERCOT slide "Loads Approved to Energize – Observations 1", verbatim: "Of the 8876 MW that have received Approval to Energize, ERCOT has observed a non-simultaneous monthly peak consumption of 3998 MW in February 2025 which is a slight decrease since January 2025." Defined by ERCOT as "the sum of the maximum value for each individual load per month".
Category
AI infrastructure power · Operating load
Object
ercot_large_load_queue
Measure
Observed large-load peak consumption (funnel_metered_peak_mw)
Family
operating_load · load
Geography
ERCOT · US
Organization
ERCOT
Claim type
Official extract
Method
Text layer of slide 6, exact sentence match; no OCR. Raw sha256 a4cc69d18ea1. Verified against the source file on 2026-09-14 by TechCarta's automated checks: table values were read twice by OCR and matched, columns sum to their printed totals, and each value was compared with the slide image. Approved for publication by C.J. Fernandes.
Source
Electric Reliability Council of Texas (ERCOT), Large Load Interconnection Status Update
Grid operator (primary) · retrieved 14 Sep 2026
https://www.ercot.com/files/docs/2026/03/05/February-TAC-Report.pdf
Archived copy (identical file)
Evidence
Outdated as of 27 Mar 2026 Past its re-check date. Describes the evidence recorded for this claim, not whether it is true. How this is decided
Re-check after
27 Mar 2026 (30 days after the as-of date)
Notes
ERCOT's sentence names "February 2025" in a deck dated 2026-02-25. Recorded verbatim; the month may be a typo in the source.
License
cite_source

Related Cartas

Conflicts with

Cite this Carta

Plain text

Electric Reliability Council of Texas (ERCOT). (2026). Large Load Interconnection Status Update [Observed large-load peak consumption: 3,998 MW, as of 2026-02-25]. Retrieved 2026-09-14, from https://www.ercot.com/files/docs/2026/03/05/February-TAC-Report.pdf. Recorded in TechCarta, CARTA-OPLOAD-ERCOT-PEAK_NONSIMULTANEOUS-2026-02-25-001. https://techcarta.com/carta/CARTA-OPLOAD-ERCOT-PEAK_NONSIMULTANEOUS-2026-02-25-001/

BibTeX

@misc{carta_opload_ercot_peak_nonsimultaneous_2026_02_25_001,
  author = {{Electric Reliability Council of Texas (ERCOT)}},
  title = {Large Load Interconnection Status Update: Observed large-load peak consumption, 3,998 MW (as of 2026-02-25)},
  year = {2026},
  howpublished = {\url{https://www.ercot.com/files/docs/2026/03/05/February-TAC-Report.pdf}},
  note = {TechCarta Carta CARTA-OPLOAD-ERCOT-PEAK_NONSIMULTANEOUS-2026-02-25-001; source retrieved 2026-09-14},
  url = {https://techcarta.com/carta/CARTA-OPLOAD-ERCOT-PEAK_NONSIMULTANEOUS-2026-02-25-001/}
}

This Carta is a TechCarta record, free to read and cite. Use of it requires citation. The underlying source belongs to its publisher.