Large-load adjustment to forecast summer peak, PECO, for 2046

1,702MW

As of 14 Jan 2026 · PJM Interconnection · Single source Permalink

Record

Filter, as published
PJM "Table B-9b: Total Adjustments to Summer Peak Load (MW) for Each PJM Zone and RTO (2026 - 2046)", row "PECO", column 2046. Summer peak load adjustments for large loads in PJM's 2026 load forecast.
Category
AI infrastructure power · Grid load forecasts
Object
pjm_summer_peak_load_forecast
Measure
Large-load adjustment to forecast summer peak (forecast_large_load_adjustment_mw)
Family
load_forecast · load
Geography
PJM · PECO · US
For year
2046
Forecast vintage
2026 Load Forecast
Organization
PJM Interconnection
Claim type
Official extract
Method
Read from the published XLSX (no OCR), sheet 1. Checked: sub-areas sum to zones and zones sum to the PJM RTO row in every year. Raw sha256 ee3b682929db. Verified against the source file on 2026-09-14 by TechCarta's automated checks: each value was re-read from its cell in the published spreadsheet and matched, and zone rows sum to the RTO row. Approved for publication by C.J. Fernandes.
Source
PJM Interconnection, Table B-9b: Total Adjustments to Summer Peak Load (MW) for Each PJM Zone and RTO (2026 - 2046)
Grid operator (primary) · retrieved 14 Sep 2026
https://www.pjm.com/-/media/DotCom/planning/res-adeq/load-forecast/total-load-adjustments-breakdown.xlsx
Archived copy (identical file)
Evidence
Single source Describes the evidence recorded for this claim, not whether it is true. How this is decided
Re-check after
18 Feb 2027 (400 days after the as-of date)
Notes
PJM's 2026 Load Forecast Report (p. 4): "Near-term forecast years need 'firm' commitments, such as Electric Service Obligation (ESO)/Construction Commitments (CC), while longer-term projects will be considered 'non-firm' and will be derated."
License
cite_source

Cite this Carta

Plain text

PJM Interconnection. (2026). Table B-9b: Total Adjustments to Summer Peak Load (MW) for Each PJM Zone and RTO (2026 - 2046) [Large-load adjustment to forecast summer peak, PECO, for 2046: 1,702 MW, as of 2026-01-14]. Retrieved 2026-09-14, from https://www.pjm.com/-/media/DotCom/planning/res-adeq/load-forecast/total-load-adjustments-breakdown.xlsx. Recorded in TechCarta, CARTA-LOADFC-PJM-PECO_LLADJ_2046-2026-01-14-001. https://techcarta.com/carta/CARTA-LOADFC-PJM-PECO_LLADJ_2046-2026-01-14-001/

BibTeX

@misc{carta_loadfc_pjm_peco_lladj_2046_2026_01_14_001,
  author = {{PJM Interconnection}},
  title = {Table B-9b: Total Adjustments to Summer Peak Load (MW) for Each PJM Zone and RTO (2026 - 2046): Large-load adjustment to forecast summer peak, PECO, for 2046, 1,702 MW (as of 2026-01-14)},
  year = {2026},
  howpublished = {\url{https://www.pjm.com/-/media/DotCom/planning/res-adeq/load-forecast/total-load-adjustments-breakdown.xlsx}},
  note = {TechCarta Carta CARTA-LOADFC-PJM-PECO_LLADJ_2046-2026-01-14-001; source retrieved 2026-09-14},
  url = {https://techcarta.com/carta/CARTA-LOADFC-PJM-PECO_LLADJ_2046-2026-01-14-001/}
}

This Carta is a TechCarta record, free to read and cite. Use of it requires citation. The underlying source belongs to its publisher.