  "carta_id": "CARTA-OPLOAD-ERCOT-PEAK_NONSIMULTANEOUS-2026-03-13-001",
  "spec_version": "0.4.0",
  "family": "operating_load",
  "domain": "load",
  "object": "ercot_large_load_queue",
  "metric": "funnel_metered_peak_mw",
  "value_num": 3883,
  "unit": "MW",
  "as_of": "2026-03-13",
  "geo_iso_or_ba": "ERCOT",
  "geo_country": "US",
  "filter": "ERCOT slide \"Loads Approved to Energize – Observations 1\", verbatim: \"Of the 9042 MW that have received Approval to Energize, ERCOT has observed a non-simultaneous monthly peak consumption of 3883 MW in March 2025 which is a slight decrease since February 2025.\" Defined by ERCOT as \"the sum of the maximum value for each individual load per month\".",
  "organization": "ERCOT",
  "claim_type": "official_extract",
  "method": "Text layer of slide 6, exact sentence match; no OCR. Raw sha256 e152e34d90e3. Verified against the source file on 2026-09-14 by TechCarta's automated checks: table values were read twice by OCR and matched, columns sum to their printed totals, and each value was compared with the slide image. Approved for publication by C.J. Fernandes.",
  "source_id": "ERCOT_LARGE_LOAD",
  "source_name": "Electric Reliability Council of Texas (ERCOT)",
  "source_document_title": "Large Load Interconnection Status Update",
  "source_url_or_id": "https://www.ercot.com/files/docs/2026/03/12/March-TAC-Report.pdf",
  "source_retrieved_on": "2026-09-14",
  "source_class": "iso_primary",
  "source_sha256": "e152e34d90e3cc0fa46f1bbda9d54fac78e8b7dc37a5901ee625ad0b7923dee1",
  "source_archive_url": "https://web.archive.org/web/20260702164630/https://www.ercot.com/files/docs/2026/03/12/March-TAC-Report.pdf",
  "source_archive_match": "exact",
  "topic": "operating_load",
  "stale_after_days": 30,
  "notes": "ERCOT's sentence names \"March 2025\" in a deck dated 2026-03-13. Recorded verbatim; the month may be a typo in the source.",
  "license": "cite_source",
  "is_example": false,
  "relations": {
    "conflicts": [
      {
        "id": "CARTA-OPLOAD-ERCOT-OBSERVED_ENERGIZED-2026-03-13-001",
        "kind": "definition_drift"
      }
    ],
    "derived_from": [],
    "inputs_to": [],
    "supersedes": null,
    "superseded_by": null,
    "cites": [],
    "cited_by": []
  },
  "segment": "ai_infrastructure_power",
  "evidence_status_on_build_date": "outdated",
  "citation": {
    "plain": "Electric Reliability Council of Texas (ERCOT). (2026). Large Load Interconnection Status Update [Observed large-load peak consumption: 3,883 MW, as of 2026-03-13]. Retrieved 2026-09-14, from https://www.ercot.com/files/docs/2026/03/12/March-TAC-Report.pdf. Recorded in TechCarta, CARTA-OPLOAD-ERCOT-PEAK_NONSIMULTANEOUS-2026-03-13-001. https://techcarta.com/carta/CARTA-OPLOAD-ERCOT-PEAK_NONSIMULTANEOUS-2026-03-13-001/",
    "bibtex": "@misc{carta_opload_ercot_peak_nonsimultaneous_2026_03_13_001,\n  author = {{Electric Reliability Council of Texas (ERCOT)}},\n  title = {Large Load Interconnection Status Update: Observed large-load peak consumption, 3,883 MW (as of 2026-03-13)},\n  year = {2026},\n  howpublished = {\\url{https://www.ercot.com/files/docs/2026/03/12/March-TAC-Report.pdf}},\n  note = {TechCarta Carta CARTA-OPLOAD-ERCOT-PEAK_NONSIMULTANEOUS-2026-03-13-001; source retrieved 2026-09-14},\n  url = {https://techcarta.com/carta/CARTA-OPLOAD-ERCOT-PEAK_NONSIMULTANEOUS-2026-03-13-001/}\n}"
  }
}