  "carta_id": "CARTA-LOADQ-ERCOT-DC_SHARE-2026-03-26-001",
  "spec_version": "0.5.0",
  "family": "large_load_queue",
  "domain": "load",
  "object": "ercot_large_load_queue",
  "metric": "load_dc_share",
  "value_num": 87.6,
  "unit": "percent",
  "as_of": "2026-03-26",
  "geo_iso_or_ba": "ERCOT",
  "geo_country": "US",
  "filter": "ERCOT slide \"Large Load Interconnection Requests\", chart \"Large Loads by Project Type\", pie chart label for category \"Data Center\" (share of tracked large load, with MW).",
  "organization": "ERCOT",
  "claim_type": "official_extract",
  "method": "OCR (RapidOCR, 2 agreeing passes) of the chart label on slide 3. Raw sha256 15ac8d6a3a8b. Verified against the source file on 2026-09-14 by TechCarta's automated checks: table values were read twice by OCR and matched, columns sum to their printed totals, and each value was compared with the slide image. Approved for publication by C.J. Fernandes.",
  "source_id": "ERCOT_LARGE_LOAD",
  "source_name": "Electric Reliability Council of Texas (ERCOT)",
  "source_document_title": "ERCOT Update to the Texas Legislature, Large Load Interconnection Requests",
  "source_url_or_id": "https://www.ercot.com/files/docs/2026/04/01/ERCOT_LargeLoad_Update_April2026_B-C_-Hearing.pdf",
  "source_retrieved_on": "2026-09-14",
  "source_class": "iso_primary",
  "source_sha256": "15ac8d6a3a8b99a1011c8be2e6254ccbdc66656745a787cc946f2b7c1382aa5d",
  "source_archive_url": "https://web.archive.org/web/20260607030544/https://www.ercot.com/files/docs/2026/04/01/ERCOT_LargeLoad_Update_April2026_B-C_-Hearing.pdf",
  "source_archive_match": "exact",
  "topic": "large_load_interconnection",
  "stale_after_days": 30,
  "notes": "The label's share and MW imply a denominator of about 406,199 MW; the queue total on the same deck's table is 410,618 MW.",
  "license": "cite_source",
  "is_example": false,
  "relations": {
    "conflicts": [],
    "derived_from": [],
    "inputs_to": [],
    "supersedes": null,
    "superseded_by": null,
    "cites": [],
    "cited_by": []
  },
  "segment": "ai_infrastructure_power",
  "evidence_status_on_build_date": "outdated",
  "citation": {
    "plain": "Electric Reliability Council of Texas (ERCOT). (2026). ERCOT Update to the Texas Legislature, Large Load Interconnection Requests [Data-center share of queued load: 87.6%, as of 2026-03-26]. Retrieved 2026-09-14, from https://www.ercot.com/files/docs/2026/04/01/ERCOT_LargeLoad_Update_April2026_B-C_-Hearing.pdf. Recorded in TechCarta, CARTA-LOADQ-ERCOT-DC_SHARE-2026-03-26-001. https://techcarta.com/carta/CARTA-LOADQ-ERCOT-DC_SHARE-2026-03-26-001/",
    "bibtex": "@misc{carta_loadq_ercot_dc_share_2026_03_26_001,\n  author = {{Electric Reliability Council of Texas (ERCOT)}},\n  title = {ERCOT Update to the Texas Legislature, Large Load Interconnection Requests: Data-center share of queued load, 87.6\\% (as of 2026-03-26)},\n  year = {2026},\n  howpublished = {\\url{https://www.ercot.com/files/docs/2026/04/01/ERCOT_LargeLoad_Update_April2026_B-C_-Hearing.pdf}},\n  note = {TechCarta Carta CARTA-LOADQ-ERCOT-DC_SHARE-2026-03-26-001; source retrieved 2026-09-14},\n  url = {https://techcarta.com/carta/CARTA-LOADQ-ERCOT-DC_SHARE-2026-03-26-001/}\n}"
  }
}